
Nine months into a three-year construction timeline, nearly a quarter-billion dollars has been spent on Scotia Place so far, an official with the project said Thursday. Read More
Nine months into a three-year construction timeline, nearly a quarter-billion dollars has been committed toward Scotia Place so far.
Nine months into a three-year construction timeline, nearly a quarter-billion dollars has been committed toward Scotia Place so far.

Article content
Nine months into a three-year construction timeline, nearly a quarter-billion dollars has been spent on Scotia Place so far, an official with the project said Thursday.
Article content
Article content
To date, $232 million, or 28 per cent of costs, have been committed toward the approximately $900-million arena and event centre that will replace the Saddledome in Victoria Park.
Article content
Most of the construction work completed on Scotia Place so far has been below-ground. Shoring and excavation are 90 per cent complete, and roughly 1,100 structural piles have been drilled and installed.
Article content
Story continues below
Article content
Foundation and below-ground construction began last month. By the time excavation is complete, crews will have removed more than 308,000 cubic metres of dirt.
Article content
Article content
“Just this week, the first concrete foundation was poured and another milestone was hit,” project lead Bob Hunter said Thursday.
Article content
“We’re down to ice level now. We still have a ways to go — it’s a very big and deep hole.”
Article content
By late fall, Hunter said, crews hope to be back at ground level, and Calgarians should start to see steel and exterior structure going up.
Article content
In 2026, crews will enclose the building, secure it and waterproof it so interior construction can begin. That process will take roughly a year and half, with an anticipated completion date of fall 2027.
Article content
“It’s an exciting time in the neighbourhood, to put it mildly,” Hunter said.
Article content
Tariff avoidance
Article content
Many of the project team’s discussions in recent months have centred on trying to avoid the financial effect of U.S.-imposed tariffs, according to Hunter.
Article content
Story continues below
Article content
While President Donald Trump recently announced a 90-day pause on tariffs, Hunter said it’s impossible to know what will happen in the ongoing trade war between Canada and the United States.
Article content
“We just hope that (reprieve) continues after the next three-month pause ,” he said.
Article content
To lessen the effect of a trade war on the project’s budget, Hunter said the team has tried to source as much construction material through Canadian suppliers as possible.
Article content
He cited an $80-million contract with Canadian supplier Walters for raw steel that comes from Europe, but is being fabricated in Hamilton, Ont. That contract was awarded in February.
Article content
Local firms were awarded the excavation and concrete contracts, which Hunter said will further avoid the effect of tariffs.
Article content
The project also requires 41,000 cubic metres of concrete, 9,000 metric tonnes of rebar and 5,000 kilometres of wire, Hunter added.
Article content
“We’re trying to lock down the procurement process as quickly as possible,” he said. “All the major elements of construction, such as electrical and mechanical, have now been awarded.”
Discover more from World Byte News
Subscribe to get the latest posts sent to your email.